Summary0000756: Duration of totality of lunar eclipses
DescriptionI believe there is an error in the calculation of the duration of totality reported in the almanac for lunar eclipses. For example, the eclipse of 21 december is reported a lasting 37 minutes, which is too short. My impression is that the almanac is calculating the time from the begining of totality to maximum eclipse, and not to end of totality. In this case, it seems OK. I checked both the 21st Dec and the 15th June 2011, and contrasted them with the NASA calculator and with Cartes simulation times, and that seems to be the case.

I haven't checked other info in the almanac, but it may be worth checking.
TagsNo tags attached.

Activities

Patrick Chevalley

10-12-06 17:43

administrator   ~0001467

Yes, all this time are half duration of the eclipse.
This is indicated in the column header but maybe is not clear enough.
The column must be read :

| Semi Duration |
|Partial|Totality|
| | |

I try to find a better solution.

 

Guillermo Abramson

10-12-06 18:26

reporter   ~0001468

You are right. I get it now. But "Semi" and "Duration", both left justified in their own columns, are not clear enough. Thanks!

Patrick Chevalley

11-06-13 11:18

administrator   ~0001636

I change the calendar to display full duration for lunar eclipse as this is more convenient.

revision 1761:
http://svn.origo.ethz.ch/viewvc/skychart?view=rev&revision=1761

Issue History

Date Modified Username Field Change
10-12-06 16:43 Guillermo Abramson New Issue
10-12-06 17:43 Patrick Chevalley Note Added: 0001467
10-12-06 17:43 Patrick Chevalley Assigned To => Patrick Chevalley
10-12-06 17:43 Patrick Chevalley Status new => assigned
10-12-06 17:43 Patrick Chevalley Product Version 0.3.0 => 3.2
10-12-06 17:43 Patrick Chevalley Target Version 0.3.0 => 3.4
10-12-06 18:26 Guillermo Abramson Note Added: 0001468
11-06-13 11:18 Patrick Chevalley Note Added: 0001636
11-06-13 11:18 Patrick Chevalley Status assigned => resolved
11-06-13 11:18 Patrick Chevalley Resolution open => fixed
11-06-13 11:18 Patrick Chevalley Fixed in Version 0.3.0 => 3.3 SVN
11-09-03 14:48 Patrick Chevalley Status resolved => closed